Wonderful job by all, very professional and our new door looks great
Domestic Garden Decking
Location: Amber Valley
Contract Duration: 10 days
REDESIGN DECKING AREA
Day 1 - Old decking removed and area levelled, rubbish removed
Day 2 - Plans made with customer and area marked out to customer requirements , foundations prepared for posts.
Day 3 - posts and skeleton frame fitted, first fix electric fitted for lighting
Day 4 -6 - decking boards laid.
Day 7 - 2nd fix electrics for lighting and outdoor electrical sockets .
Day 8 - fit glass panels
DAY 9-10- finishing touches
This project transformed the customers outside space to create a sophisticated
area for entertaining, they were pleased with the look created.